Reducing CO2 emissions: Liebherr LTM 1650-8.1 mobile crane installs silo at cement plant

Heidelberg Materials is investing heavily in the reduction of CO2 emissions in cement production.

Reducing CO2 emissions: Liebherr LTM 1650-8.1 mobile crane installs silo at cement plant

The Liebherr LTM 1650-8.1 mobile crane installs the new silo for aggregates for cement production.

  • LTM 1650-8.1 from Schmidbauer hoists loads of over 50 tonnes with a 31.5 metre luffing jib
  • New silo system adds aggregates to cement production to reduce clinker and therefore CO2 emissions

A Liebherr LTM 1650-8.1 mobile crane from the crane and heavy haulage contractor Schmidbauer GmbH & Co. KG has now installed a silo at the Schelklingen cement plant for storing aggregates that can reduce the proportion of clinker in the cement.

Clinker is fired from limestone in a rotary kiln at 1,450 degrees Celsius. This process releases CO2 which damages the climate. “The less clinker we need for cement production, the less CO2 is released into the atmosphere,” explains Frank Hartwig, the Project Manager responsible for new builds and modifications at Heidelberg Materials’ Schelklingen plant. “Therefore, we want to replace the clinker in the cement with other suitable materials. We can store 1,500 tonnes of them in the new silo. The dosing station in the so-called penthouse above it feeds the aggregate straight into the cement production process.”


Reducing CO2 emissions: Liebherr LTM 1650-8.1 mobile crane installs silo at cement plant
The filling station, known as the penthouse, is levelled with a special chain system that can be adjusted in length pneumatically.

Schmidbauer GmbH & Co. KG sent its one-and-a-half-year-old Liebherr LTM 1650-8.1 with three transport vehicles for the counterweight and two vehicles for the luffing jib from Munich to Upper Swabia to install the new silo system. The two crane operators Stephan Pirner and Robert Halsner used the Liebherr 8-axle crane for initial assembly work and the two main hoists, each of around 53 tonnes. They set up the crane with 145 tonnes of ballast and a 31.5 metre luffing jib for the work.

After installing the bottom part, the actual silo was put in position. A day later, the penthouse, which weighed around the same, was mounted on top of the silo. The biggest challenge was to attach the load to the sloping penthouse roof. A special chain system, whose length can be adjusted pneumatically, was used to level the huge component.


Reducing CO2 emissions: Liebherr LTM 1650-8.1 mobile crane installs silo at cement plant
The penthouse is carefully positioned on top of the silo.

The two crane operators are full of praise for the Liebherr LTM 1650-8.1. “This is the best crane I have ever used,” says Stephan Pirner, who has worked for Schmidbauer for 27 years and has operated large cranes from various manufacturers for 23 years. “The set-up process is particularly efficient. Liebherr has designed it in such a way that very little physical work is required from the crane operators.” His colleague Robert Halsner, a crane operator for seven years, agrees: “The LTM 1650-8.1 is really user-friendly and very flexible to use with VarioBase® and VarioBallast®. And it is extremely powerful.”


Reducing CO2 emissions: Liebherr LTM 1650-8.1 mobile crane installs silo at cement plant
Crane operators Stephan Pirner (right) and Robert Halsner are pleased with how easy the LTM 1650-8.1 is to operate.

Project Manager Hartwig is also pleased with the installation of the new silo system: “In recent years, our company has made a number of investments for the future here at the site. More projects are already planned, so it's good to be able to rely on competent partners.”